ALTANA PHARMA, Oranienburg, Germany
New extension of tablets production – administration building
Employer / Designer
Client:
ALTANA Pharma, Oranienburg
Architekt:
HWP Stuttgart
Project data
Technical costs:
8.35 million EUR
Construction costs:
15 million EUR
GFA:
14 700 sq. m
GCV:
90 000 cu. m
Project description
- Demineralized water supply
- Central compressed air
- Waste water neutralization system
- Distilled water warm and cold
- Air compressor
- Steam generator (for production + HVAC)
- 2 NH3-Cooling machines (2 MW)
- HVAC-System total 325 000 cu. m/h
- Pressure control for production areas
- Production of ultrapure water